Department of Health and Social Care · Health

New Hospital Programme

Deliver the reset New Hospital Programme through a series of construction waves, including priority replacement of hospitals affected by reinforced autoclaved aerated concrete.

Tracker assessment
Methodology statusIn progress
Tracker interpretationMixed
Current evidence7 open; 9 in construction; 7 business cases approved in-year
Reporting periodFinancial year 2025–26

What the evidence shows

FactThe 2025–26 annual report documented delivery stages, £9.6 billion of Spending Review funding and an amber NISTA delivery-confidence assessment.

CalculationNo aggregate completion percentage: open, construction and business-case counts are separate delivery stages

AssessmentHospitals are open and in construction, but the programme remains amber and much delivery lies in later waves extending to 2040.

Limitations

  • The programme counts schemes, hospitals and construction projects in different contexts; they are not interchangeable.
  • A delivery-stage baseline matching the annual report categories at the January 2025 reset has not yet been imported.
  • An amber NISTA rating reflects programme delivery confidence, not a prediction that every scheme will miss its date.

Money allocated, an announcement or an activity is not treated by itself as evidence of delivery. Timing and correlation do not establish causation.

Evidence and revision trail

Baseline: 46 schemes in the January 2025 reset programme; a comparable count by delivery stage at reset is awaiting data integration

Target: 46 programme schemes with scheme-specific delivery windows

Next milestone: 2026–27 Wave 1 business cases, construction starts and the next annual programme report (2027-07-01)