New Hospital Programme
Deliver the reset New Hospital Programme through a series of construction waves, including priority replacement of hospitals affected by reinforced autoclaved aerated concrete.
Tracker assessmentWhat the evidence shows
FactThe 2025–26 annual report documented delivery stages, £9.6 billion of Spending Review funding and an amber NISTA delivery-confidence assessment.
CalculationNo aggregate completion percentage: open, construction and business-case counts are separate delivery stages
AssessmentHospitals are open and in construction, but the programme remains amber and much delivery lies in later waves extending to 2040.
Limitations
- The programme counts schemes, hospitals and construction projects in different contexts; they are not interchangeable.
- A delivery-stage baseline matching the annual report categories at the January 2025 reset has not yet been imported.
- An amber NISTA rating reflects programme delivery confidence, not a prediction that every scheme will miss its date.
Money allocated, an announcement or an activity is not treated by itself as evidence of delivery. Timing and correlation do not establish causation.
Evidence and revision trail
Baseline: 46 schemes in the January 2025 reset programme; a comparable count by delivery stage at reset is awaiting data integration
Target: 46 programme schemes with scheme-specific delivery windows
Next milestone: 2026–27 Wave 1 business cases, construction starts and the next annual programme report (2027-07-01)
- DHSC New Hospital Programme annual report 2025–26 — Official programme annual report
- New Hospital Programme plan for implementation — Official reset scope and waves